... | ... | @@ -8,6 +8,8 @@ The overall versioning strategy proposal and process for OSDU milestone release. |
|
|
|
|
|
[**Patch Process**](https://community.opengroup.org/osdu/documentation/-/wikis/Patch-Process)
|
|
|
|
|
|
[**Dev Environments**](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/Environments)
|
|
|
|
|
|
## Release Branches
|
|
|
|
|
|
Each release of OSDU libraries and services will have a major/minor version pair (such as "1.0") that represents the release. Release numbers that match across different services are meant to be considered a package -- that is, they were released at the same time. The specific numbers in the version are increased with each release (in the normal way), but importantly are not synchronized to any other milestone name, including monikers such as "R3" or "M1".
|
... | ... | @@ -66,13 +68,14 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the |
|
|
![Release Process](uploads/ad6e073a3e3c980ebd19be11579a0989/image.png)
|
|
|
|
|
|
Please note that:
|
|
|
* Feature freeze is for completion of features development on common code
|
|
|
* Between ‘Feature Freeze’ and ‘Code Tagging Start’:
|
|
|
* No new features
|
|
|
* `Feature Freeze` is for completion of features development on common code. No new features should be developed for this milestone after this date.
|
|
|
* Between `Feature Freeze` and `Code Tagging Start`:
|
|
|
* No new features should be developed but can still be merged if pending reviews and approvals
|
|
|
* Only bug fixes, CSP specific changes, stabilizing pipeline
|
|
|
* Release coordinator (current that is David D.) completes the code tagging
|
|
|
* Deployed to pre shipping date is target date for CSP teams to deploy the tagged milestone baseline into pre shipping env so that pre shipping team is ready to execute the tests.
|
|
|
* Public release date is after the validation from pre shipping team. The date may change depending on the validation results.
|
|
|
* On the day of `Code Tagging Start`, the release branch is forked from the default (main/master) branch. Release coordinator completes the code tagging.
|
|
|
* As soon as code tagging is completed, the tags are deployed to the `QA/Testing Platform Validation` environment.
|
|
|
* `Deployed to Pre Shipping` date is the target date for CSP teams to deploy the tagged milestone baseline into pre-shipping env so that preshipping team is able to execute UAT.
|
|
|
* Public release date is after the confirmation and validation from pre shipping team. The date may change depending on the validation results.
|
|
|
|
|
|
You may find additional notes about "CSP deployment to QA/Testing (aka "Platform Validation") and Preship environments" in this document.
|
|
|
https://gitlab.opengroup.org/osdu/pmc/docs/-/blob/master/Planning/OSDU_Community_Milestone_Release_Process.docx
|
... | ... | @@ -91,17 +94,17 @@ _Note that the dates below might change depending on various reasons, announceme |
|
|
|
|
|
|Milestones|Feature Freeze| Code Tagging Start |Code Tagging Completed|Deployed to Pre Shipping|Public Release|
|
|
|
|----------|--------------|--------------------|----------------------|------------------------|--------------|
|
|
|
|M17 |17-Mar-23 |31-Mar-23 |13-Apr-23 |19-Apr-23 |10-May-23 |
|
|
|
|M16 |27-Jan-23 |03-Feb-23 |17-Feb-23 |22-Feb-23 |15-Mar-23 |
|
|
|
|M15 |11-Nov-22 |02-Dec-22 |13-Dec-22 |16-Dec-22 |13-Jan-23 |
|
|
|
|M14 |23-Sep-22 |30-Sep-22 |7-Oct-22 |14-Oct-22 |09-Nov-22 |
|
|
|
|M13 |22-Jul-22 |4-Aug-22 |12-Aug-22 |19-Aug-22 |09-Sep-22 |
|
|
|
|M17 |17-Mar-23 |31-Mar-23 |13-Apr-23 |19-Apr-23 |10-May-23 |
|
|
|
|M16 |27-Jan-23 |03-Feb-23 |17-Feb-23 |22-Feb-23 |15-Mar-23 |
|
|
|
|M15 |11-Nov-22 |02-Dec-22 |13-Dec-22 |16-Dec-22 |13-Jan-23 |
|
|
|
|M14 |23-Sep-22 |30-Sep-22 |07-Oct-22 |14-Oct-22 |09-Nov-22 |
|
|
|
|M13 |22-Jul-22 |04-Aug-22 |12-Aug-22 |19-Aug-22 |09-Sep-22 |
|
|
|
|M12 |20-May-22 |27-May-22 |24-Jun-22 |28-Jun-22 |12-Jul-22 |
|
|
|
|M11 |18-Mar-22 |28-Mar-22 |1-Apr-22 |15-Apr-22 |03-May-22 |
|
|
|
|M11 |18-Mar-22 |28-Mar-22 |01-Apr-22 |15-Apr-22 |03-May-22 |
|
|
|
|M10 Patch | |11-Mar-22 |18-Mar-22 |18-Mar-22 |25-Mar-22 |
|
|
|
|M10 |14-Jan-22 |21-Jan-22 |28-Jan-22 |11-Feb-22 |4-Mar-22 |
|
|
|
|M10 |14-Jan-22 |21-Jan-22 |28-Jan-22 |11-Feb-22 |04-Mar-22 |
|
|
|
|M9 |15-Oct-21 |22-Oct-21 |29-Oct-21 |12-Nov-21 |10-Dec-21 |
|
|
|
|M8 | |27-Aug-21 |3-Sep-21 |17-Sep-21 |30-Sep-21 |
|
|
|
|M8 | |27-Aug-21 |03-Sep-21 |17-Sep-21 |30-Sep-21 |
|
|
|
|M7 | |16-Jul-21 | |30-Jul-21 |20-Aug-21 |
|
|
|
|M6 | |28-May-21 | | |02-Jul-21 |
|
|
|
|M5 | |9-Apr-21 | | |21-May-21 | |
|
|
|M5 | |09-Apr-21 | | |21-May-21 | |