## Development timeline for milestones
|
|
|
Each OSDU milestone starts with about 1.5 months of development, following the code tagging process, deployment into pre shipping environment by CSP teams, and validation in pre shipping environment.
|
|
|
|
|
|
|
|
|
|
|
|
The code freeze date is important milestone for development teams. Below is the current planned date for code freeze for upcoming milestones:
|
|
|
|
|
|
- M5:
|
|
|
- M6: end of May - May 28, 2021
|
|
|
- M7: mid of Jul - Jul 16, 2021
|
|
|
- M8: end of Aug - Aug 27, 2021
|
|
|
|
|
|