@@ -28,12 +28,16 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the
...
@@ -28,12 +28,16 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the


The code freeze date is important milestone for development teams. Below is the current planned date for code freeze for upcoming milestones:
Below is the current planned date for upcoming OSDU milestone releases. Note that:
-
Code freeze date is for development teams to complete the new function development and integration in this release.
-
M5: code frozen on Apr 9, 2021
-
Public release date is after the validation from pre shipping team. The date may change depending on the validation results.
-
M6: end of May (May 28, 2021)
-
M7: mid of Jul (Jul 16, 2021)
|Milestones|Code freeze date for Dev teams|Public release date|
-
M8: end of Aug (Aug 27, 2021)
|----------|------------------------------|-------------------|
|M5 |Apr 9, 2021 |May 2021 |
|M6 |May 28, 2021 (end of May) |Jun 25, 2021 |
|M7 |Jul 16, 2021 (mid of Jul) |Aug 13, 2021 |
|M8 |Aug 27, 2021 (end of Aug) |Sep 24, 2021 |