Changes
Page history
Update Release Strategy
authored
May 19, 2021
by
Chris Zhang
Show whitespace changes
Inline
Side-by-side
Release-Strategy.md
View page @
bec9fe06
...
...
@@ -28,12 +28,16 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the

The code freeze date is important milestone for development teams. Below is the current planned date for code freeze for upcoming milestones:
-
M5: code frozen on Apr 9, 2021
-
M6: end of May (May 28, 2021)
-
M7: mid of Jul (Jul 16, 2021)
-
M8: end of Aug (Aug 27, 2021)
Below is the current planned date for upcoming OSDU milestone releases. Note that:
-
Code freeze date is for development teams to complete the new function development and integration in this release.
-
Public release date is after the validation from pre shipping team. The date may change depending on the validation results.
|Milestones|Code freeze date for Dev teams|Public release date|
|----------|------------------------------|-------------------|
|M5 |Apr 9, 2021 |May 2021 |
|M6 |May 28, 2021 (end of May) |Jun 25, 2021 |
|M7 |Jul 16, 2021 (mid of Jul) |Aug 13, 2021 |
|M8 |Aug 27, 2021 (end of Aug) |Sep 24, 2021 |
# Creation Process
...
...
...
...