Update Release Strategy authored by Chris Zhang's avatar Chris Zhang
...@@ -26,11 +26,11 @@ All release branches will have at least a ".0" patch, but may gain additional ta ...@@ -26,11 +26,11 @@ All release branches will have at least a ".0" patch, but may gain additional ta
## Development timeline for milestones ## Development timeline for milestones
Each OSDU milestone starts with about 1.5 months of development, following the code tagging process, deployment into pre shipping environment by CSP teams, and validation in pre shipping environment. Each OSDU milestone starts with about 1.5 months of development, following the code tagging process, deployment into pre shipping environment by CSP teams, and validation in pre shipping environment.
![OSDUMilestoneRelease](uploads/703b4ea8c804cc001505221ee24058c2/OSDUMilestoneRelease.png)
The code freeze date is important milestone for development teams. Below is the current planned date for code freeze for upcoming milestones: The code freeze date is important milestone for development teams. Below is the current planned date for code freeze for upcoming milestones:
- M5: - M5: mid of Apr - Apr 9, 2021
- M6: end of May - May 28, 2021 - M6: end of May - May 28, 2021
- M7: mid of Jul - Jul 16, 2021 - M7: mid of Jul - Jul 16, 2021
- M8: end of Aug - Aug 27, 2021 - M8: end of Aug - Aug 27, 2021
... ...
......