... | ... | @@ -26,11 +26,11 @@ All release branches will have at least a ".0" patch, but may gain additional ta |
|
|
## Development timeline for milestones
|
|
|
Each OSDU milestone starts with about 1.5 months of development, following the code tagging process, deployment into pre shipping environment by CSP teams, and validation in pre shipping environment.
|
|
|
|
|
|
|
|
|
![OSDUMilestoneRelease](uploads/703b4ea8c804cc001505221ee24058c2/OSDUMilestoneRelease.png)
|
|
|
|
|
|
The code freeze date is important milestone for development teams. Below is the current planned date for code freeze for upcoming milestones:
|
|
|
|
|
|
- M5:
|
|
|
- M5: mid of Apr - Apr 9, 2021
|
|
|
- M6: end of May - May 28, 2021
|
|
|
- M7: mid of Jul - Jul 16, 2021
|
|
|