... | ... | @@ -36,6 +36,7 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the |
|
|
Below is the current planned date for upcoming OSDU milestone releases. Note that:
|
|
|
|
|
|
* Code freeze date is for development teams to complete the new function development and integration in this release.
|
|
|
* Deploy to pre shipping date is for CSP teams to deploy the tagged milestone baseline into pre shipping env so that pre shipping team can execute the tests.
|
|
|
* Public release date is after the validation from pre shipping team. The date may change depending on the validation results.
|
|
|
|
|
|
|Milestones|Code freeze date for Dev teams|Deploy to Pre Shipping|Public release date|
|
... | ... | @@ -44,6 +45,10 @@ Below is the current planned date for upcoming OSDU milestone releases. Note tha |
|
|
|M6 |May 28, 2021 (end of May) | |Jul 2, 2021 |
|
|
|
|M7 |Jul 16, 2021 (mid of Jul) |Jul 30, 2021 |Aug 13, 2021 |
|
|
|
|M8 |Aug 27, 2021 (end of Aug) |Sep 17, 2021 |Sep 24, 2021 |
|
|
|
|M9 |Oct 22, 2021 (mid of Oct) |Nov 5, 2021 |Nov 19, 2021 |
|
|
|
|M10 |Jan 14, 2022 (mid of Jan) |Jan 28, 2022 |Feb 11, 2022 |
|
|
|
|
|
|
* M10 cycle is longer with consideration of Christmas and new year holiday
|
|
|
|
|
|
# Creation Process
|
|
|
|
... | ... | |