@@ -36,6 +36,7 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the
Below is the current planned date for upcoming OSDU milestone releases. Note that:
* Code freeze date is for development teams to complete the new function development and integration in this release.
* Deploy to pre shipping date is for CSP teams to deploy the tagged milestone baseline into pre shipping env so that pre shipping team can execute the tests.
* Public release date is after the validation from pre shipping team. The date may change depending on the validation results.
|Milestones|Code freeze date for Dev teams|Deploy to Pre Shipping|Public release date|
...
...
@@ -44,6 +45,10 @@ Below is the current planned date for upcoming OSDU milestone releases. Note tha