## Current planned dates for upcoming OSDU milestone releases
_Note that the dates below might change depending on various reasons, announcement will be made in [PMC Slack channel](https://opensdu.slack.com/archives/C010VA9RD25) for further communication_
_Note that the dates below might change depending on various reasons, announcement will be made in _[_PMC Slack channel_](https://opensdu.slack.com/archives/C010VA9RD25)_ for further communication_
#### :snail: Updated Mercury to Venus Releases Cadence starting M23 as announced in the 31-Jan-2024 Focal Point meeting
_**PLEASE BARE IN MIND THE FOLLOWING TABLE WILL BE SOON DEPRECATED IN FAVOR OF THE ONE CENTRALISED IN PMC PORTAL - [HERE](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/home)**_
**_PLEASE BARE IN MIND THE FOLLOWING TABLE WILL BE SOON DEPRECATED IN FAVOR OF THE ONE CENTRALISED IN PMC PORTAL - _**[**_HERE_**](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/home)
| Milestones | Code Dev Start | Feature Freeze | Code Tagging Start | Code Tagging Completed | Deployed to Pre Shipping | Public Release |
These pages are generated by scripts to report the status of the tagging process. They are mostly relevant to the developers while releases are being prepared.
@@ -144,14 +139,13 @@ Each OSDU milestone starts with about 1.5 months of development, followed by the
Please note that:
-`Feature Freeze` is the target date for the completion of feature development on common code. No new feature should be planned and developed for this milestone release after this date.
- Between `Feature Freeze` and `Code Tagging Start`:
- No new features should be developed but existing merge requests (MRs) can still be merged if pending reviews and approvals
- Only bug fixes, CSP-specific changes, stabilizing pipeline
- On the day of `Code Tagging Start`, the release branch is forked from the default (main/master) branch. Any new feature/code development in the default branch now goes towards the next milestone release. Release coordinator completes the code tagging.
- As soon as code tagging is completed, the [tags](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/Release-Strategy#tagging-notes) are deployed to the `QA/Testing Platform Validation` environment.
-`Deployed to Pre Shipping` date is the target date for CSP teams to complete deployment of the tagged milestone baseline into pre-shipping environment so that pre-shipping team is able to execute UAT.
-`Public Release` date is after the confirmation and validation from pre-shipping team. The date may change depending on the validation results.
You may find additional notes about "CSP deployment to QA/Testing (aka "Platform Validation") and Preship environments" in this document.
-`Feature Freeze` is the target date for the completion of feature development on common code. No new feature should be planned and developed for this milestone release after this date.
- Between `Feature Freeze` and `Code Tagging Start`:
- No new features should be developed but existing merge requests (MRs) can still be merged if pending reviews and approvals
- Only bug fixes, CSP-specific changes, stabilizing pipeline
- On the day of `Code Tagging Start`, the release branch is forked from the default (main/master) branch. Any new feature/code development in the default branch now goes towards the next milestone release. Release coordinator completes the code tagging.
- As soon as code tagging is completed, the [tags](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/Release-Strategy#tagging-notes) are deployed to the `QA/Testing Platform Validation` environment.
-`Deployed to Pre Shipping` date is the target date for CSP teams to complete deployment of the tagged milestone baseline into pre-shipping environment so that pre-shipping team is able to execute UAT.
-`Public Release` date is after the confirmation and validation from pre-shipping team. The date may change depending on the validation results.
You may find additional notes about "CSP deployment to QA/Testing (aka "Platform Validation") and Preship environments" in this document. https://gitlab.opengroup.org/osdu/pmc/docs/-/blob/master/Planning/OSDU_Community_Milestone_Release_Process.docx