... | ... | @@ -27,6 +27,7 @@ Each release branch will contain tags, one for each patch released under that ve |
|
|
|
|
|
* [R3 Milestone 6](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/Release-Notes#milestone-6-july-2-2021)
|
|
|
* [R3 Milestone 7](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/Release-Notes#milestone-7-august-20-2021)
|
|
|
* [R3 Milestone 8 \[DRAFT\]](https://community.opengroup.org/osdu/governance/project-management-committee/-/wikis/Release-Notes#darft-milestone-8-september-24-2021-tentative)
|
|
|
|
|
|
## Development timeline for milestones
|
|
|
|
... | ... | @@ -39,9 +40,8 @@ Below is the current planned date for upcoming OSDU milestone releases. Note tha |
|
|
* Code freeze date is for development teams to complete the new function development and integration in this release.
|
|
|
* Deployed to pre shipping date is target date for CSP teams to deploy the tagged milestone baseline into pre shipping env so that pre shipping team is ready to execute the tests.
|
|
|
* Public release date is after the validation from pre shipping team. The date may change depending on the validation results.
|
|
|
|
|
|
| Milestones | Code freeze date for Dev teams | Deployed to Pre Shipping | Public release date |
|
|
|
|----------|------------------------------|-------------------|-------------------|
|
|
|
|------------|--------------------------------|--------------------------|---------------------|
|
|
|
| M5 | Apr 9, 2021 | | May 2021 |
|
|
|
| M6 | May 28, 2021 (end of May) | | Jul 2, 2021 |
|
|
|
| M7 | Jul 16, 2021 (mid of Jul) | Jul 30, 2021 | Aug 20, 2021 |
|
... | ... | |